TEMCO 6000 project · Barcelona

Roof waterproofing in Barcelona

Substrate preparation, perimeter repairs and cold-applied polyurea waterproofing, followed by aliphatic protection with aggregate for a slip-resistant finish.

Finish with aliphatic protection and aggregate · Barcelona
TEMCO 6000 project · Barcelona

Intervention stages

The ceramic substrate and old waterproofing were deteriorated. Preparation included sanding and repairs, with particular attention to the perimeter, before applying the new system.

Cracks in the perimeter walls were repaired and junctions sealed with polyurethane sealant. The system included a vapour barrier and primer before the cold-applied polyurea membrane.

The continuous membrane was finished with grey aliphatic protection and aggregate for slip resistance. The photographs show the development of the substrate and critical junctions.

Roof before intervention · Barcelona
Roof before intervention
Treatment of perimeter junctions · Barcelona
Treatment of perimeter junctions
Finish with aliphatic protection and aggregate · Barcelona
Finish with aliphatic protection and aggregate

Each building needs its own assessment. This case study describes work carried out on one specific project.