TEMCO 6000 project · Sant Cugat del Vallès
Treating pool joints and cracks in Sant Cugat
Local treatment of joints, cracks and formwork tie holes using resin injection and repair mortars. This project did not include a full coating of the pool shell.

Intervention stages
The intervention addressed specific pool-shell details: joints, cracks and formwork tie holes. Initial photographs show the areas before local treatment.
Resin injection and mortar repairs were performed at the specified points. Treatment was adapted to those discontinuities and junctions.
Finish photographs document the repaired points. A full coating of walls and floor was not carried out; these images do not represent complete treatment of the pool shell.
Each building needs its own assessment. This case study describes work carried out on one specific project.